Fairfax-Bolinas Road CONDITION UPDATES, thank you for your patience: At milepost 5.73, Fairfax-Bolinas Road will be open on weekdays and weekends from 12/16/24 through 1/1/25 (weather permitting), with traffic controlled through a single lane with alternating access. This is to accommodate the holiday traffic. From 1/2/25 through 1/5/25, the road will be closed at milepost 5.73 to allow for construction activities as the project nears completion, weather permitting. After 1/5/25, it is anticipated that the road will be closed from Azalea Hill to Ridgecrest on weekdays only. By mid-January, the project is expected to be completed and the roadway will fully reopen. See project webpage for details.

120 North Redwood Heat Pump Replacements

This is a completed project. You are in the Archived Projects section of the website. Active projects can be found on the Projects webpage.

Description

Overview

Replacement of eight deteriorated heat pump units at 120 North Redwood will correct issues with the heating and cooling of the building. The work is part of a larger series of improvements to the Health and Human Services facility which began in 2019.

Funding

The project cost is $420,000. It is funded by Health & Human Services with support from Federal and State Public Assistance revenue.

Public impacts

There will be minor impacts to access during the work. The completed project will improve the public and private areas of the buildings.

Timeline

Spring 2022

  • Construction underway

Summer 2022

  • Anticipated project completion