Sea View Ave Stormwater Drainage Improvement

Description

Overview

The project will improve the drainage of stormwater in order to reduce the risk of erosion and flooding in the area of the south intersection of W. Sea View Avenue and Sea View Avenue. This work includes the installation of drop inlets, new pipes, and rock.

Funding

The estimated cost is $150,000 and is funded by the County's Road & Bridge Fund.

Traffic impacts

One lane of Sea View Avenue will be closed from 90 to 120 Sea View Avenue for four weeks. Traffic will be controlled through a single lane during the construction phase.

Timeline

October 2024

  • Planning phase

January 13, 2025

  • Construction phase expected to begin

Early/Mid February 2025

  • Expected completion of construction phase