Fairfax-Bolinas Road CONDITION UPDATES, thank you for your patience: At milepost 5.73, Fairfax-Bolinas Road will be open on weekdays and weekends from 12/16/24 through 1/1/25 (weather permitting), with traffic controlled through a single lane with alternating access. This is to accommodate the holiday traffic. From 1/2/25 through 1/5/25, the road will be closed at milepost 5.73 to allow for construction activities as the project nears completion, weather permitting. After 1/5/25, it is anticipated that the road will be closed from Azalea Hill to Ridgecrest on weekdays only. By mid-January, the project is expected to be completed and the roadway will fully reopen. See project webpage for details.

120 North Redwood Repairs

This is a completed project. You are in the Archived Projects section of the website. Active projects can be found on the Projects webpage.

Description

Overview

The project includes repairs to the breezeway and siding at 120 N. Redwood. The project will replace damaged safety rails on the building, repair water intrusion damage and replace broken windows. Work on the third-floor breezeway includes repairs to deteriorated railings, installation of new windows, and repairs to stucco and exterior siding.

Funding

The project cost is $225,000. It is funded by Health & Human Services with support from Federal and State Public Assistance revenue.

Public impacts

None expected, but day to day work may require adjustments to access.

Timeline

March 2022

  • Start of construction

Fall 2022

  • End of construction