Fairfax-Bolinas Road CONDITION UPDATES, thank you for your patience: At milepost 5.73, Fairfax-Bolinas Road will be open on weekdays and weekends from 12/16/24 through 1/1/25 (weather permitting), with traffic controlled through a single lane with alternating access. This is to accommodate the holiday traffic. From 1/2/25 through 1/5/25, the road will be closed at milepost 5.73 to allow for construction activities as the project nears completion, weather permitting. After 1/5/25, it is anticipated that the road will be closed from Azalea Hill to Ridgecrest on weekdays only. By mid-January, the project is expected to be completed and the roadway will fully reopen. See project webpage for details.

Bolinas Road Slide Repair at milepost 1.16

Description

This is a completed project. You are in the Archived Projects section of the website. Active projects can be found on the Projects webpage.

Overview

The March 2023 storms triggered multiple landslides and roadway damage along Bolinas Road. The damaged locations have been receiving repairs in order of urgency. The road is the sole route for hundreds of homes and provides critical access for wildland firefighting. The road is also the only way to reach water treatment facilities that supply drinking water for one-third of Marin Water’s customers, approximately 90,000 residents.

A slide caused by the storms forced the closure of the eastbound lane of Bolinas Road at milepost 1.16. The slide repair project at milepost 1.16 included a retaining wall, guardrailing, cable railing, and an asphalt drainage dike.

Funding

The $980,000 project was covered by the County's Road & Bridge fund, and approximately 88% is expected to be reimbursed by the Federal Highway Administration's Emergency Repair Program.

Traffic impacts

Construction work hours were weekdays from 8 a.m. to 6 p.m. with traffic control measures in place. For the duration of the project, traffic flowed through a single lane with alternating two-way traffic. Traffic delays were limited to no more than seven minutes.

Timeline

May 2024

  • Start of construction phase

June 2024

  • Project completed