Fairfax-Bolinas Road CONDITION UPDATES, thank you for your patience: At milepost 5.73, Fairfax-Bolinas Road will be open on weekdays and weekends from 12/16/24 through 1/1/25 (weather permitting), with traffic controlled through a single lane with alternating access. This is to accommodate the holiday traffic. From 1/2/25 through 1/5/25, the road will be closed at milepost 5.73 to allow for construction activities as the project nears completion, weather permitting. After 1/5/25, it is anticipated that the road will be closed from Azalea Hill to Ridgecrest on weekdays only. By mid-January, the project is expected to be completed and the roadway will fully reopen. See project webpage for details.

Bretano Way Retaining Wall Replacement

This is a completed project. You are in the Archived Projects section of the website. Active projects can be found on the Projects webpage.

Description

Overview

The retaining wall along the median of Bretano Way was deteriorating at 130-132 Bretano Way. The project included demolition of the old wall and replacing it with a new, 100-foot-long wall to protect the condition of the roadway.

Funding

The construction estimate was $182,000 and was funded by the County's Road & Bridge fund.

Traffic Impacts

Egress to and from Bretano Way was not impacted. However, there were occasional temporary closures of the eastbound direction of Bretano Way at the construction zone.

Pedestrian and bicycle access was maintained during the construction phase. There was no street parking available between 126-132 Bretano Way for the duration of the construction work. Emergency vehicles were granted access at all times.

Timeline

August 5, 2024

  • Construction began

August 13 and 15, 2024

  • Temporary closure from noon to 2pm of the eastbound direction between 128-134 Bretano Way.

September 2024

  • Completion of construction