Fairfax-Bolinas Road CONDITION UPDATES, thank you for your patience: At milepost 5.73, Fairfax-Bolinas Road will be open on weekdays and weekends from 12/16/24 through 1/1/25 (weather permitting), with traffic controlled through a single lane with alternating access. This is to accommodate the holiday traffic. From 1/2/25 through 1/5/25, the road will be closed at milepost 5.73 to allow for construction activities as the project nears completion, weather permitting. After 1/5/25, it is anticipated that the road will be closed from Azalea Hill to Ridgecrest on weekdays only. By mid-January, the project is expected to be completed and the roadway will fully reopen. See project webpage for details.

Juvenile Hall Toilet Replacement

This is a completed project. You are in the Archived Projects section of the website. Active projects can be found on the Projects webpage.

Description

Overview

This project entailed replacing 5 toilet units and related plumbing, as well as enlarging the existing maintenance access points to allow for improved future maintenance needs.

Funding

Probation Department funded the project cost of $250,000.

Public impacts

None

Timeline

Winter 2022

  • Construction begins

Spring 2023

  • Construction complete