Fairfax-Bolinas Road CONDITION UPDATES, thank you for your patience: At milepost 5.73, Fairfax-Bolinas Road will be open on weekdays and weekends from 12/16/24 through 1/1/25 (weather permitting), with traffic controlled through a single lane with alternating access. This is to accommodate the holiday traffic. From 1/2/25 through 1/5/25, the road will be closed at milepost 5.73 to allow for construction activities as the project nears completion, weather permitting. After 1/5/25, it is anticipated that the road will be closed from Azalea Hill to Ridgecrest on weekdays only. By mid-January, the project is expected to be completed and the roadway will fully reopen. See project webpage for details.

Marin Civic Center HVAC System Assessment

This is a completed assessment project. You are in the Archived Projects section of the website. Active projects can be found on the Projects webpage.

Description

Overview

Marin County Civic Center air handling units, and supporting HVAC components, are reaching the end of useful life; 96% of AC units are original to the building. The HVAC System Assessment was conducted to determine an overall refurbishment/replacement plan taking into account all equipment as an integrated system. The assessment considered overall cost, energy efficiency as it relates to the Marin County Climate Action Plan 2030, and new or retrofit equipment that will meet industry standards for durability and life expectancy. The final report presented a recommended plan and a multiyear capital plan for design and construction.

Funding

Estimated $200,000 and funded by the Capital Improvement Program fund.

Public impacts

None

Timeline

Fall 2022

  • Design assessment

Summer 2023

  • Completion of assessment and final report
Close window