Fairfax-Bolinas Road CONDITION UPDATES, thank you for your patience: At milepost 5.73, Fairfax-Bolinas Road will be open on weekdays and weekends from 12/16/24 through 1/1/25 (weather permitting), with traffic controlled through a single lane with alternating access. This is to accommodate the holiday traffic. From 1/2/25 through 1/5/25, the road will be closed at milepost 5.73 to allow for construction activities as the project nears completion, weather permitting. After 1/5/25, it is anticipated that the road will be closed from Azalea Hill to Ridgecrest on weekdays only. By mid-January, the project is expected to be completed and the roadway will fully reopen. See project webpage for details.

Rosal Way Storm Drain Improvement

Description

Overview

The purpose of this project is to alleviate water ponding that occurs after heavy storms on Rosal Way in Santa Venetia (area of unincorporated San Rafael), between Adrian Way and Labrea Way. The scope includes installing three new catch basins and storm drains to connect to the existing storm drain system. This project is not intended to solve flooding issues that occur within the Santa Venetia community.

Funding

The estimated $145,000 project will be funded by the County's Road & Bridge Fund.

Traffic Impacts

It is expected that there will be traffic impacts to residents on Rosal Way and detour routes will be used. Specific traffic control measures and impact details will be publicized once construction plans are approved.

Timeline

October 10, 2024

  • Construction phase started

Late November, 2024

  • Expected completion of construction phase