Fairfax-Bolinas Road CONDITION UPDATES, thank you for your patience: At milepost 5.73, Fairfax-Bolinas Road will be open on weekdays and weekends from 12/16/24 through 1/1/25 (weather permitting), with traffic controlled through a single lane with alternating access. This is to accommodate the holiday traffic. From 1/2/25 through 1/5/25, the road will be closed at milepost 5.73 to allow for construction activities as the project nears completion, weather permitting. After 1/5/25, it is anticipated that the road will be closed from Azalea Hill to Ridgecrest on weekdays only. By mid-January, the project is expected to be completed and the roadway will fully reopen. See project webpage for details.

San Geronimo Paving Project

Description

Overview

This rehabilitation projects includes pavement resurfacing on approximately 11.1 "lane miles" of roadway, asphalt dig-outs to repair areas of isolated base failure, pavement grinding, minor storm drainage improvements, and roadway striping.

The streets in San Geronimo and Woodacre that will be addressed are: Arroyo Road, Garden Way, Barranca Road, Meadow View Lane, Castle Rock Avenue, Oak Grove Avenue, Castro Street, Railroad Avenue, Chaparral Lane, Redwood Canyon Drive, Elm Avenue, Spring Avenue, Fire Road, and Tamal Road.

Funding

The estimated $5 million project is funded by the County's Road & Bridge Fund.

Traffic impacts

Construction will take place during the daytime hours with traffic control measures.  Work shift road closures are required for grinding and again for paving.  For residential roads, it is expected that each road will be closed twice during the project, for a maximum of 8 hours per day. For collector roads, the road will be completed with lane closures.

Project information notices will be issued by the contractor once their schedule is established. Property owners/residents along the roads scheduled for paving are also given advance written notifications ahead of any work that requires their road to be closed so that residents have time to adequately prepare.  After paving the road, the public will notice an immediate improvement to the road’s aesthetics and rideability.

Timeline

August 2023 through October 2023

  • First phase of construction

May 2024 through July 2024

  • Second phase of construction